Valued Partners,
The ASE 4 SUA has been signed which has allowed us to commence the building of the ASE 4 road and drilling pad. Due to inclement weather we have not been able to lay the wooden matting, which is our all-weather road we have used for the ASE 1, 2 & 3 well locations.
During this downtime, our team has painted the BDW 650 rig and conducted maintenance and other system checks.
The weather forecast is showing rain until Thursday to Friday, yet with dry weather predicted over the weekend and beyond, we will look to complete the road and pad, then set up the BDW 650 rig and prepare to set surface casing, then spud.