Valued Partners,
Currently, the all-weather road is being laid to the ASE 4 drilling pad, which like all of our current and future wells on our lease, allows our rigs, equipment, and trucks to access our well pads and facilities regardless of the weather conditions.
Once road construction has been completed, our BDW 650 rig will be moved off the ASE 3 location to the ASE 4 drilling pad. The rig will then be set-up, safety and system checks will be completed, and the drilling process will commence.