Valued Partners,
The BDW 650 rig will be moved from the ASE 3 pad to the ASE 4 location once the road to the ASE 4 has been constructed using additional timber matting that we have used throughout the site with great success. This all-weather road has been essential to enable the operation to continue at the current pace, as Seminole County has experienced significant rainfall over the past months.
The completion unit will then be mobilised and commence the final stages of completing the well in preparation for the pump jack and ultimately oil & gas production.