Valued Partners,
The ASE 4 SUA has been signed which has allowed us to commence the building of the ASE 4 road and drilling pad. Due to inclement weather we have not been able to lay the wooden matting, which is our all-weather road we have used for the ASE 1, 2 & 3 well locations.
The weather forecast is showing rain until Thursday to Friday, yet with dry weather predicted over the weekend and beyond, we will look to complete the road and pad. Once the BDW 650 rig has been moved off the ASE 3 location, we will commence the ASE 3 completion process, with production tests to follow.