Valued Partners,

Due to the heavy rainfall and thunderstorms experienced in Seminole County, completion of the ASE 1 & 2 wells has been delayed. Unfortunately, this has subsequently affected the construction of the ASE 3 pad and road as well.

The weather forecast for the next week looks very promising and we plan to move the new drilling rig (BDW 650) on to the pad next week to commence drilling. As of this morning, our operating team has began construction of the road to the ASE 3. Please see the video below.