Valued Partners,

In preparation of bringing the ASE 1 & 2 online, the tank batteries, separator, and heat treater installations are being finished today. The gas pipeline is now also active, so we are ready to bring the wells online for any gas production as well. The ASE 1 & 2 are near the highway crossover so it will not take more than a day or two to hook them up once we get the wells online.

We will be scheduling the two wells for completion shortly. We have included images from our operations team below.