Valued Partners,

The operating team has made significant progress this week on the ASE 2. They spent the majority of Monday placing a downhole pump and running rods, and the ASE 2 is now ready for a pumpjack.

As you are aware, the ASE 1's pumpjack is installed, and an order has been placed for a motor, which is scheduled to arrive this Friday. Both wells are near completion and we expect to be in production soon.