7th March 2025, Update

March 7, 2025

Dear Valued Investor Partners,

Below is a summary of the latest developments at the Parker Fee Project, including production updates and operational improvements.

‍

December Revenue & Distribution Update

As outlined in the latest Settlement Statement (see below), 1,094 barrels of oil were sold, totalling 6 full truckloads in December.

‍

Operational Improvements & Cost Savings

  • The waterline installation is now fully operational, eliminating the need for water transportation.
  • As outlined in last month’s update, this is expected to reduce costs by approximately $2,300 monthly.

‍

Production & Well Deepening Update

  • February production has seen a notable increase, with a total of seven loads sold.
  • This improvement is largely attributed to recent capital investments, which have enhanced overall operational efficiency.

‍

Well Deepening Development

  •       We have engaged a new cable tool operator and requested a quote to secure the most competitive pricing.  
  •       Over the coming weeks, we will finalize agreements with all necessary contractors, aiming to commence the deepening of the A-2A well at the earliest opportunity. 

‍

New Oil Purchaser

  • As of February 2nd, we have secured a new oil purchaser for our Parker Fee oil.
  • This transition has resulted in an improved price per barrel, approximately 3% higher than our previous purchaser.

‍

Next Update

Further updates will be provided in our next portal, scheduled for release on the last day of the first week of the month.

‍