August 5, 2022

August 5, 2022

Valued Partners,

During the past few months, our team has been searching for 4-1/2 inch casing that was planned to go inside the ASE 5#1H's 6-1/4 inch wellbore, but due to a global shortage, it has been almost impossible to find, with extended delivery wait times, as well as up to a 40% increase in the cost.

In order to be solution focused, in the past 1-2 weeks we have been in communication with Hadaway Engineering and a hydraulic fracturing consultant regarding alternative options.

We are now able to report that we have a solution, which is to use the 3-1/2 inch drill pipe we used for the well, cement in place, then complete the perforating followed by the hydraulic fracturing and flowback/production. The consultants have stated that they have seen this exact process (using the 3-1/2 drill pipe) completed on multiple occasions and have produced impressive results.

Deane Pierce (Petroleum Engineer) has found a company with the correct perforating tool that will operate within a 3-1/2 inch casing. The next steps for the ASE 5#1H well are as follows:

     
  • Order the perforating tool
  •  
  • Wait for our engineering team (Hadaway) and Deane to make adjustments to the frac design, and then finalise the correct cement process
  •  
  • Book-in and conduct the cement process and allow to cure for 5-7 days
  •  
  • Perforate and hydraulic fracture the entire horizontal section (5,000 ft) of the well with up to 21 stages, noting the original design was only 13-14 stages